overturns permit revocation
| | |

CA overturns permit revocation of Villar’s SIPCOR

MANILA, Philippines – The Court of Appeals (CA) has overturned the Energy Regulatory Commission’s (ERC) 2025 decision revoking the operating permits of Villar-linked S.I. Power Corporation (SIPCOR), ruling that the regulator denied the company procedural due process when it ordered the generator to halt its Siquijor operations.

But the appellate court did not rule or absolve SIPCOR of the operational failures that led to Siquijor’s power crisis, and its July 24 ruling does not itself authorize the company to restart its plants.

“Lest it be misunderstood, this Court does not absolve SIPCOR of any violations nor diminish the ERC’s power to revoke PAOs,” Associate Justice Bonifacio Pascua penned for the CA’s Special Seventh Division.

“The power situation in Siquijor demanded swift and decisive action from the ERC. Even so, due process cannot be sacrificed for mere expediency. All told, the ERC failed to afford due process in revoking the PAOs of SIPCOR’s generation units,” he added.

The court found that the ERC denied SIPCOR procedural due process by using what had been presented as a fact-finding investigation to revoke its operating authorities without formally notifying the company that its permits were at risk, while also relying on evidence SIPCOR was not given a chance to contest.

ERC Chairperson Francis Juan told Rappler that the agency would challenge the ruling by filing a motion for reconsideration through the Office of the Solicitor General.

The case stemmed from prolonged outages in Siquijor in 2025, when residents and businesses endured hours-long brownouts that disrupted hospitals, schools, and the tourism-dependent island economy. Energy Secretary Sharon Garin said the island suffered 568 power interruptions, or an average of 31 outages a month.

The ERC opened an investigation in June 2025 after its inspectors found operational deficiencies and a consumer complained of daily outages. SIPCOR, the Province of Siquijor Electric Cooperative or PROSIELCO, and the National Power Corporation were called to a July 3, 2025, public hearing and ordered to submit documents on power supply, maintenance, fuel inventory, and other operational issues.

The CA, however, said those proceedings were consistently framed as fact-finding. The ERC never issued SIPCOR the show-cause order required by its own rules, which should have specified the alleged violations, their legal basis, and the possible penalty.

“An opportunity to participate does not automatically cure the lack of specific notice of the real issue at stake,” the CA said.

The court also found that the ERC relied on documents submitted after the July hearing — including an August 6, 2025, letter from the energy secretary, a University of the Philippines National Engineering Center audit report, and an ERC supplemental memorandum — without giving SIPCOR an opportunity to contest them.

The appellate court also questioned how the shutdown was implemented. The ERC had already issued provisional authorities to operate (PAOs) to replacement generator TOTALPower before its decision against SIPCOR was promulgated. After serving the decision to SIPCOR on August 29, 2025, the regulator ordered it to cease operations by 3 pm that same day, even though ERC rules generally give parties 15 days before a decision becomes final and unappealable.

For these reasons, the CA granted SIPCOR’s petition and “reversed and set aside” the ERC’s August 28, 2025, decision.

The CA decision in CA-G.R. SP No. 191696 was promulgated on July 24 but was disclosed to the public only on Tuesday, August 18, through Premiere Island Power REIT’s (PREIT) filing with the Philippine Stock Exchange (PSE).

Must Read

Siquijor’s decades-long search for stable power


Siquijor’s decades-long search for stable power

Does this mean SIPCOR can continue operations?

The CA decision may have voided the ERC’s revocation of SIPCOR’s license, but this does not mean SIPCOR can operate immediately. 

For one, the PAOs that allow SIPCOR’s three power plants to operate have already expired:

  • Siquijor Diesel Power Plant: PAO effective March 16, 2025 to March 15, 2026
  • Lazi Diesel Power Plant: PAO effective June 17, 2025 to June 16, 2026
  • Siquijor Diesel Power Plant Expansion: PAO effective August 5, 2024 to August 4, 2025 SIPCOR began pre-filing for renewal on June 20, 2025 and formally applied on July 10, 2025.

Even if SIPCOR regains authority to operate, it’s unclear whether it can resume supplying PROSIELCO, the electric cooperative that acts as the island’s electric distribution utility. PROSIELCO has already signed a 15-year power supply agreement with Vivant Energy subsidiary Isla Dilaab Energy Corporation for 11 MW of capacity.

“Regardless of the final outcome of that case, the term of SIPCOR’s provisional authority to operate had already expired. Besides, its power supply agreement with PROSIELCO was already terminated,” Juan told Rappler on Wednesday, August 19.

In other words, SIPCOR’s return remains unlikely for now given that its permits have expired and PROSIELCO has already locked in a long-term power supply deal with another generator.

“I doubt if it will be able to secure a new PSA with the coop since the latter has already conducted its [competitive selection process] and executed with another generator for all its supply requirement,” Juan told Rappler.

The CA decision essentially voided the ERC’s revocation of SIPCOR’s license. But this may not necessarily mean SIPCOR can operate immediately.

SIPCOR itself has acknowledged the uncertainty. In a disclosure to the PSE on Tuesday, August 18, PREIT said SIPCOR was still awaiting these next steps before it could move to resume operations. Trading in PREIT shares was subsequently halted by the PSE following the disclosure.

“We shall continue to keep PREIT informed of material developments, particularly on the finality and execution of the Decision and the restoration of SIPCOR’s authority to operate. Once these are achieved, we formally express our intention to proceed with the lifting of the suspension of the Lease Agreement dated 11 April 2022, as amended, and PREIT’s corresponding recognition of lease revenue,” SIPCOR wrote in a letter to PREIT dated August 18.

SIPCOR is wholly owned by Prime Asset Ventures Inc., the infrastructure group founded by Manny Villar, and is PREIT’s controlling stockholder and parent company. PREIT owns and leases land, buildings, and generation assets used by SIPCOR, which accounted for about 47% of PREIT’s rental income in 2025 before the lease was suspended following SIPCOR’s shutdown.

Must Read

[Vantage Point] Villar’s PREIT: When the lights go out on a dividend illusion


[Vantage Point] Villar’s PREIT: When the lights go out on a dividend illusion

Rappler.com

Similar Posts

  • |

    Senate pushes Rs617m gas project for 42 Ghotki villages

    Islamabad: After years of waiting, 42 villages located near the Badar Gas Field in District Ghotki are finally moving towards receiving natural gas as the Senate Petroleum Sub Committee pushed authorities to act on a long delayed promise linked to the Prime Minister’s Directive of 15 September 2003 and Supreme Court directions. The Sub Committee, convened by Senator Jam Saifullah Khan, expressed concern over the continued delay in providing gas facilities to villages located within five kilometres of gas producing fields. The Committee directed relevant departments and companies to ensure that previous commitments are converted into practical work without further delay. The meeting was attended by Senators Manzoor Ahmed Kakar and Haji Hidayatullah Khan along with senior officials from the Petroleum Division, Finance Division, Oil and Gas Regulatory Authority, Sui Southern Gas Company Limited, Sui Northern Gas Pipelines Limited, Oil and Gas Development Company Limited, Pakistan Petroleum Limited, Mari Energies and other stakeholders. During the meeting, the Sub Committee decided to give top priority to the gasification project for the remaining 42 villages near Badar Gas Field, District Ghotki. The estimated cost of the project is Rs617 million. The Special Secretary Petroleum Division, Finance Division officials and Chairman OGRA assured the Committee that Rs200 million would initially be released from the allocated Rs1 billion funds to start the project immediately. Managing Director Sui Southern Gas Company Limited informed the Committee that the company would provide its share of funding and begin technical planning, engineering work and procurement activities. It was decided that project activities would begin within ten days after the release of initial funds. The Committee was informed that remaining funds required for completing the project would be arranged without interruption. The Petroleum Division and Finance Division assured the Committee that financial issues would not become a reason for further delay. The Sub Committee also reviewed the wider issue of gas supply to villages located within five kilometres of gas producing fields across Pakistan. Officials informed the Committee that new policy guidelines are being prepared to implement the Prime Minister’s Directive and Supreme Court instructions regarding gasification of eligible villages. The Petroleum Division was directed to present a complete implementation plan in the next meeting. The plan will include details about funding arrangements, responsibilities of different organizations, district wise schedules and clear completion timelines for all remaining eligible villages across the country.

  • |

    Global oil prices edge higher amid incertainty over Strait of Hormuz

    Global crude oil prices moved higher on Monday as uncertainty surrounding the reopening of the Strait of Hormuz continued to influence market sentiment and raise concerns about potential disruptions to international energy supplies. According to media reports, oil prices gained during Asian trading, with investors closely monitoring developments related to the strategic waterway and the ongoing discussions over shipping arrangements. Brent crude futures climbed by more than 1%, moving above the $84-per-barrel mark. US crude oil also recorded a gain of more than 1% during the session, reflecting renewed concerns over the stability of oil shipments through the region. The Strait of Hormuz remains a major focus for global energy markets because of its importance to international oil transportation. Any prolonged disruption to shipping through the waterway could put upward pressure on crude prices and raise concerns about supplies to major importing countries. Market participants are therefore keeping a close watch on diplomatic efforts aimed at restoring normal maritime traffic. Uncertainty over when and under what conditions the waterway will fully reopen has added to volatility in crude oil markets. Iran has said that an understanding with Oman regarding the establishment of new shipping routes is nearing completion. However, Tehran has also maintained that the Strait of Hormuz will not fully reopen until additional conditions involving the United States are addressed. The conflicting positions have left traders uncertain about the timing of a broader resolution. As a result, oil markets remain sensitive to any fresh developments involving Iran, Oman, the United States and maritime traffic through the strait. A sustained increase in crude prices could have wider economic implications, particularly for countries that rely heavily on imported petroleum. Higher international oil prices can increase import bills, put pressure on foreign exchange reserves and contribute to higher domestic fuel costs.

Leave a Reply

Your email address will not be published. Required fields are marked *