balochistan flood resilience
|

Balochistan flood resilience project faces delays despite housing support progress

QUETTA: Implementation of a major World Bank-backed flood resilience programme in Balochistan is facing significant delays, with slow progress on infrastructure, climate services and housing reconstruction raising concerns about the project’s ability to meet its targets before the scheduled completion date.

The Integrated Flood Resilience and Adaptation Project (P180323), launched in the aftermath of the devastating 2022 floods, has seen mixed results. While more than 74,000 affected households have received the first tranche of financial assistance for housing reconstruction, several key components of the project remain substantially behind schedule.

According to the World Bank’s latest Implementation Status and Results Report, overall implementation progress has been downgraded to “Moderately Unsatisfactory”, while the project’s development objective continues to carry a “Moderately Satisfactory” rating.

The overall risk associated with the project remains high.

The programme was approved in May 2023 with the broader objective of helping flood-affected communities restore livelihoods, regain access to essential services and strengthen their ability to withstand future climate-related disasters.

Infrastructure work gains momentum

The project includes several major components covering community infrastructure, resilient housing, hydro-meteorological and climate services, as well as institutional strengthening and project management.

The World Bank reported some improvement in the community infrastructure component following the appointment of a dedicated project director and the strengthening of the Project Implementation Unit.

Detailed engineering designs and bidding documents are now close to completion, while procurement activities have begun.

Despite these developments, the project has yet to achieve any of the three development-objective-linked output indicators associated with the component.

The gap reflects the difference between preparatory work and actual delivery of infrastructure on the ground, with authorities still required to translate procurement and planning progress into completed projects for flood-affected communities.

Climate services remain behind schedule

Progress has also been reported in the climate-services component following the appointment of a new deputy project director and the award of a contract for Automatic Weather Stations (AWS).

However, several critical steps remain outstanding.

The onboarding of the system integrator has yet to be completed, while a number of important procurement activities are still pending.

The project aims to strengthen Balochistan’s ability to monitor weather conditions and provide timely warnings to communities exposed to floods and other climate-related hazards.

Under the programme, the authorities are targeting the installation of 110 Automatic Weather Stations and the operationalisation of four weather radars.

As of July 2026, none of the targeted weather radars had become operational.

One positive development has been the establishment of a hydrological modelling-based early warning system for hill torrents in Balochistan, which could improve preparedness in areas vulnerable to sudden flooding.

Housing component performs better

The strongest performance has been recorded under the resilient housing component.

More than 74,000 households have received the first tranche of housing assistance, providing financial support to families whose homes were damaged or destroyed by the 2022 floods.

However, the World Bank has identified several risks that could affect further progress.

These include a decision by the Project Steering Committee to limit beneficiary coverage, a funding shortfall affecting other eligible households, unresolved complaints and grievances, and communication difficulties with beneficiaries.

The World Bank warned that these issues could undermine confidence in the programme and affect its ability to reach the intended beneficiaries.

The physical reconstruction figures also show that considerable work remains.

By July 2026, only 30,226 housing units had been restored or reconstructed against the project’s target of 97,000 homes by December 2028.

This means authorities will need to significantly accelerate reconstruction during the remaining implementation period if the target is to be achieved.

Essential services target remains distant

The project also aims to restore access to essential services for flood-affected communities.

By July 2026, around 214,217 people had regained access to at least one essential service.

However, the eventual target is 1.5 million people, indicating a substantial gap between current achievements and the programme’s planned outcome.

Similarly, the project has yet to register progress against its target of improving climate resilience for 1.8 million people.

The figures suggest that while financial assistance and preparatory activities have moved forward, the broader resilience-building objectives are yet to translate into measurable results on the required scale.

Irrigation and flood protection work yet to deliver

The restoration of flood-damaged irrigation systems is another major area where implementation remains slow.

The project has a target of restoring irrigation infrastructure covering approximately 50,000 hectares.

A similar target has been set for improving flood-protection infrastructure over an area of 50,000 hectares.

However, as of July 2026, no achievement had been recorded against either target.

The lack of progress is particularly significant given the importance of irrigation to livelihoods in Balochistan, where agriculture and livestock remain major sources of income for many communities.

Restoring damaged irrigation networks is also critical to rebuilding economic activity in areas affected by the 2022 floods.

Financing constraints add pressure

Financial challenges are adding another layer of difficulty to implementation.

The project has a revised allocation of approximately $214.03 million under the IDA-73330 facility.

Of this amount, around $113.97 million, equivalent to 62.61%, has been disbursed, while approximately $68.05 million remains undisbursed.

In addition, a separate $32 million IDA-78980 facility remains completely undisbursed.

The financing position means authorities have both resources and time constraints to manage as they seek to accelerate implementation.

Bridging funding gaps for eligible beneficiaries and ensuring timely utilisation of available financing will be crucial to maintaining momentum during the remaining project period.

Grievances and communication concerns

The World Bank has also highlighted unresolved grievances and communication shortcomings as risks to the housing component.

For a project involving thousands of flood-affected households, effective communication is essential to ensure beneficiaries understand eligibility criteria, payment arrangements, construction requirements and complaint-resolution procedures.

Unresolved grievances could not only delay implementation but also create dissatisfaction among communities that expected assistance following the 2022 floods.

Authorities will therefore need to strengthen communication channels and grievance mechanisms alongside accelerating physical reconstruction.

Limited time remains

The Integrated Flood Resilience and Adaptation Project is scheduled to close on December 31, 2028.

With roughly two years remaining, the authorities face a demanding implementation schedule.

They will need to speed up procurement, complete pending technical work, address financing constraints, resolve beneficiary complaints and translate planned interventions into completed infrastructure.

The World Bank’s latest assessment indicates that the project has made some progress, particularly in housing assistance and preparatory work for community infrastructure and climate services. However, major gaps remain in achieving its core resilience targets.

The coming months will therefore be critical for determining whether the programme can move from planning and financial assistance towards large-scale physical implementation.

For Balochistan, which remains highly vulnerable to floods, extreme weather and climate-related risks, timely completion of the project is important not only for rebuilding infrastructure damaged in 2022 but also for strengthening the province’s ability to withstand future disasters.

Similar Posts

  • | |

    Rain continues across Sindh

    Intermittent rain continues to affect several parts of Sindh, including Hyderabad, Mirpurkhas, Tharparkar, Badin, Thatta and Sujawal, bringing relief from the heat but also causing water accumulation in low-lying areas. In Mirpurkhas, persistent rainfall has flooded several low-lying localities, with rainwater entering homes and creating difficulties for residents. The situation has also disrupted routine activities in affected areas. Power supply has also been affected in parts of Mirpurkhas following a fault in a high-tension transmission line. Residents have faced electricity outages as efforts continue to address the technical issue and restore the supply. Weather conditions remain unsettled across southern and southeastern Sindh, where rain-bearing clouds continue to dominate the region. Further rainfall is possible in several areas as the weather system remains active. In Karachi, light rain and drizzle were reported in several parts of the city, including Quaidabad, Malir and Gulistan-e-Johar. The showers brought cooler conditions to some localities, while residents in other areas continued to experience cloudy and humid weather. Authorities and local administrations are monitoring the situation, particularly in low-lying areas where continued rainfall could lead to further water accumulation and temporary disruption to daily life.

  • |

    China holds military drills near disputed Scarborough Shoal

    China’s military carried out joint naval and air exercises around the disputed Scarborough Shoal in the South China Sea on Saturday, saying the operations were intended to strengthen combat readiness and protect what it considers its territorial and maritime rights. The People’s Liberation Army Southern Theater Command said the drills took place in the waters and airspace surrounding the shoal, which China refers to as Huangyan Dao. The area is also claimed by the Philippines, where it is known as Bajo de Masinloc, and has long been one of the region’s most contested maritime zones. In a statement, the Chinese military said the exercises were a necessary response to actions by what it described as “certain countries” that it claimed were disrupting peace and stability in the South China Sea. The statement did not identify any country by name, but the Scarborough Shoal has remained at the centre of ongoing tensions between China and the Philippines. The Philippine embassy in Beijing did not immediately comment on the military exercises or respond to requests for a statement. According to the Chinese military, the operation was designed to test the coordination and readiness of naval and air forces while improving their ability to respond to security challenges in the region. Officials said the exercises would help strengthen China’s capability to defend its territorial claims and safeguard its maritime interests. On the same day, Chinese authorities also announced new rules governing the Huangyan Island National Nature Reserve, which was established in September 2025. State news agency Xinhua reported that the updated policy bans unauthorised fishing, mining, coral collection, giant clam harvesting and other activities considered harmful to the protected marine environment. Chinese officials said anyone found violating the new regulations would face legal action under the country’s laws. The measures are intended to strengthen environmental protection while reinforcing China’s administrative control over the disputed area. The Scarborough Shoal has been a source of repeated diplomatic and maritime disputes for years. Both China and the Philippines claim sovereignty over the area, and encounters between their coast guards and fishing vessels have frequently heightened tensions in the South China Sea. The latest military exercises are expected to draw close attention from neighbouring countries and regional observers, as competing territorial claims continue to shape security concerns in one of the world’s busiest and most strategically important waterways.

  • |

    Salman Khan reveals 16kg weight loss amid health concerns

    Salman Khan has responded to growing concern about his health after fans noticed his slimmer appearance in recent public outings and began speculating about his well-being. The Bollywood superstar recently appeared alongside his younger brother, Sohail Khan, during a television appearance where the two discussed fitness, weight loss and maintaining a healthy lifestyle. The conversation quickly drew attention after Salman commented on Sohail’s transformed physique. Noticing his brother’s leaner frame, Salman remarked that Sohail had clearly lost weight. Sohail proudly revealed that he had shed 12 kilograms and achieved a toned physique, even showing off his six-pack abs. The conversation then turned to Salman himself, who surprised viewers by sharing that he had also undergone a significant physical transformation. According to the actor, he has lost 16 kilograms, confirming that his noticeable weight loss was real rather than the result of camera angles or styling. While he did not provide details about the reason behind the weight loss, his comments appeared to reassure fans who had been worried about his health in recent weeks. Speculation surrounding Salman’s condition intensified after videos from several public appearances circulated online. Many social media users observed that the actor looked noticeably slimmer than before, with some commenting that he appeared tired or frail. The discussions quickly gained momentum, leading to widespread concern among fans. His latest remarks have now clarified that he has intentionally lost a significant amount of weight, although he did not elaborate on his fitness routine, diet or any medical reasons behind the transformation. Salman has long been known for maintaining an athletic physique and has inspired millions of fans with his dedication to fitness throughout his decades-long career. Whether for film roles or personal health, the actor has often undergone physical transformations, making fitness an important part of his public image. Despite the recent attention surrounding his appearance, Salman continues to remain busy with multiple film projects. One of his most anticipated upcoming releases is the patriotic war drama Maatrubhumi: May War Rest in Peace, previously known as Battle of Galwan. The film has reportedly undergone extensive reshoots, resulting in several changes to its release plans. While it was initially expected to arrive in 2026, recent reports suggest the release has been pushed back and may now take place in 2027. The actor is also preparing for another major project alongside South Indian star Nayanthara. The film, currently being referred to by its working title SVC63, is being directed by Vamshi Paidipally. Although an official title has yet to be announced, the makers are reportedly targeting an Eid 2027 release. With multiple high-profile films in development, Salman remains one of Bollywood’s busiest stars. His recent comments about losing 16 kilograms have helped address widespread speculation, offering fans reassurance while also highlighting his continued focus on fitness as he prepares for his upcoming projects.

  • | |

    Christian Convery calls Anne Hathaway his ‘hero’

    Actor Christian Convery has opened up about his experience filming the sci-fi thriller The End of Oak Street, describing the production as both exciting and emotionally demanding while praising his co-star Anne Hathaway. The film features Convery alongside Hathaway, Ewan McGregor and Maisy Stella. The story follows the Platt family as they struggle to survive after their neighbourhood is mysteriously displaced into an unfamiliar and dangerous environment. Speaking about the filming experience, Convery said the production involved a sharp contrast between lighthearted family scenes and emotionally intense sequences. He explained that scenes involving ordinary family moments, such as a neighbourhood party or a meal together, were enjoyable to film. However, extended periods of emotionally heavy scenes became exhausting for the cast. The young actor said the demanding nature of the production helped the cast connect with their characters on a deeper level. According to Convery, the actors were placed under considerable physical and emotional pressure during filming, which helped them portray the fear, tension and uncertainty experienced by their characters more convincingly. Convery also discussed how the cast developed a believable family dynamic on screen. He said there was no special formula for creating chemistry because the cast members naturally connected when they first met. He credited the table read, preparation sessions and regular discussions for helping the actors understand their relationships within the story. The cast also spent time together away from the set, including during meals and weekends, which further strengthened their bond. The actor said the close relationship eventually extended beyond the principal cast, describing the entire production team as a large family. Convery also spoke warmly about working with Anne Hathaway, admitting that he initially felt nervous because she had been one of his acting heroes for many years. He said Hathaway treated him as a professional colleague rather than simply as a young actor. That approach helped him feel respected and gave him an opportunity to learn from her while maintaining a clear distinction between their on-screen relationship and their real-life professional relationship. Convery has been working in the entertainment industry since childhood. He said a major turning point came when he was around nine years old and landed the lead role in Sweet Tooth, a project he filmed over several years in New Zealand. He explained that the experience encouraged him to take acting more seriously and develop a deeper understanding of filmmaking. He began studying different performances, directors and classic films while learning more about the creative process behind cinema. Despite his early success, Convery said he remains focused on improving his craft and believes actors should remain grounded and recognise that there is always more to learn.

  • | | |

    Narathiwat Province in Thailand’s Deep South Escalates Martial Law Powers After Deadly Attack Kills Five Border Rangers

    NARATHIWAT, Thailand Security forces in Thailand’s southern border province of Narathiwat have intensified the application of martial law powers following a deadly assault on a checkpoint that left five paramilitary rangers dead and several civilians injured. On the evening of July 22nd, 2026, at approximately 6:45 p.m., a group of about six attackers dressed in […]

  • | |

    Pakistan information commission declares Pakistan …

    ISLAMABAD: The Pakistan Information Commission (PIC) has declared the Pakistan Bar Council (PBC) a public body under the Right of Access to Information Act, 2017, and directed it to provide within 15 days information sought regarding lawyers’ degrees, licence cancellations, government grants and governing body proceedings. The order was issued in appeal titled Saddia Mazhar vs Pakistan Bar Council, by Chief Information Commissioner Shoaib Ahmad Siddiqui and Information Commissioner Ijaz Hassan Awan. The applicant had sought eight categories of information, including province-wise numbers of PBC members or licence holders; those who had submitted attested degrees; lawyers whose licences were cancelled for failing to submit attested educational documents; and those whose licences were cancelled over fake degrees. She also sought copies of circulars and notifications concerning degree attestation, details of federal and provincial government grants received since 2020, including amounts and dates, and a copy of the latest minutes of the PBC Governing Body meeting. In its reply to the Commission, that the PBC maintained that it was an autonomous statutory body generating its own funds and did not fall within the definition of a public body. Its representatives argued that the government exercised neither financial nor administrative control over it, while acknowledging that the Attorney General for Pakistan is its ex officio member. The Commission rejected the PBC’s position, holding that it is a statutory organisation established under the Legal Practitioners and Bar Councils Act, 1973, and performs important public functions relating to legal education, recognition of law degrees and regulation of legal practitioners. It also observed that Bar Councils receive public funds or government grants and their offices are located in public buildings. The PIC ruled that the PBC falls within the definition of a public body under Section 2(ix)(g) and (h) of the Right of Access to Information Act, 2017. It further held that none of the eight information requests attracted an exemption under the law. The Secretary, Pakistan Bar Council, was consequently directed to provide the requested information within 15 days of receiving the order. The case was adjourned until September 2, 2026.

Leave a Reply

Your email address will not be published. Required fields are marked *